Llano River Crossing
The Texas Tech University Center (TTU) located on the banks of the South Llano River, in Junction, TX, provides academic, research and service programs to expand educational, economic and cultural opportunities throughout the Texas Hill Country region.
The Housley Construction Group was selected to place new water, sewer and gas lines, in the rock bed under the Llano River, for the Texas Tech University facility. Scheduled academic programs and graduate research commitments required that the project had to complete in only thirty (30) days. The project was successfully completed in less than thirty (30) days.
The utility crossing of the South Llano River was done at the site of a new state highway bridge which was still under construction. In order to cross the river we had to divert half the width of the Llano River to facilitate our work. The placing of the new utility services required trenching in solid bed rock a 30" wide X 5' deep trench a distance of over 300 feet across the river. After placing the new utility steel encasements and utility lines it took over 400 yards of concrete to bed the pipes and re-fill the trench. The men and equipment in the picture are actually standing on the rock bed of the Llano River after half the rivers width was diverted.
Typical university classroom and research buildings. Terrain is very rugged and wildlife is plentiful.
First half of the South Llano River diversion completed which caused increased flow on the un-diverted side of the river.
Work underway to hammer and excavate a 30” X 5’ X 300’ utility trench in solid bed rock.
Work underway to hammer and excavate a 30” X 5’ X 300’ utility trench in solid bed rock.
Half of the utility trench across the river completed.
Steel casing being placed in the bottom of the bed rock trench.
Temporary water, sewer and gas utility lines had to be placed across the new bridge during construction.
TX dot surveyor at work to ensure the top of the steel casing was at exactly the right depth before bedding and capping with concrete.
Exit point for the steel casing on the North side of the South Llano River ready for concrete pour from crane over the side of the bridge.